TOMAHAWK CREEK WASTEWATER TREATMENT FACILITY EXPANSION
SCHEDULE
Construction started April 2018 and will continue through the spring of 2022.
The following activities will be occurring over the next 2 months
May 2022 - June 2022
-
Commissioning Sidestream
-
Final grading North of Overflow Channel & Digesters
-
Final Completion Punchlist activities
Previous activities
Apr 2022 - May 2022
-
Commissioning Sidestream
-
Final grading North of Overflow Channel & Digesters
-
Final Completion Punchlist activities
-
NOTE: We anticipate that the trail along Lee Blvd will be open and accessible to the public in June 2022.
Previous activities
Mar 2022 - Apr 2022
-
Commissioning Solids Train (Dewatering & Sidestream)
-
Performance Testing Equipment (Centrifuges & RDTs)
-
Final grading North of Overflow Channel & Digesters
-
Final Completion Punchlist activities
-
Substantial Completion
Previous activities
Feb 2022 - Mar 2022
-
Commissioning Solids Train (Sidestream)
-
Performance Testing Equipment
-
Final grading North of Overflow Channel & Digesters
-
Punchlist activities
-
Demobilize jobsite trailers
Previous activities
Jan 2022 - Feb 2022
-
Commissioning Solids Train
-
Performance Testing Equipment
-
Install site fencing
-
Punchlist activities
-
Demobilize jobsite trailers
Previous activities
Dec 2021 - Jan 2022
-
Commissioning Solids Train
-
Install site fencing
-
Site grading around digesters
-
Punchlist activities
-
Demobilize jobsite trailers
Previous activities
Nov - Dec
2021
-
Site paving – Asphalt topcoat
-
Finishing installation of interior process mechanical equipment and piping
-
Finishing installation of interior ductwork, electrical conduit, and plumbing piping
-
Commissioning Liquids Train
-
Facility Startup – Digester Complex & Sidestream
-
Commissioning Solids Train
-
Install the bike trail
-
Install site fencing
-
Insulating the digester covers
-
Punchlist Activities
Previous activities
Oct - Nov
2021
-
Site paving – Asphalt
-
Installation of interior process mechanical equipment and piping
-
Spread topsoil & Seeding (weather permitting)
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Interior finishes
-
Facility Startup – Digester Complex & Sidestream
-
Digester Lid #3 Fabrication
-
Punchlist Activities
-
Commissioning Liquids Train
-
Previous activities
Sept - Oct
2021
-
Site paving – Concrete & asphalt
-
Installation of interior process mechanical equipment and piping
-
Spread topsoil (weather permitting)
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Interior finishes
-
Facility Startup – Digester Complex & Sidestream
-
Digester Lid #3 Fabrication
-
Punchlist Activities
-
Commissioning Liquids Train
-
Previous activities
Aug - Sept
2021
-
Site paving – Concrete & asphalt
-
Installation of interior process mechanical equipment and piping
-
Raise site to sub grade and spread topsoil (weather permitting)
-
Process and electrical underground utilities
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Interior finishes
-
Facility Startup – Digester Complex
-
Digester Lid #3 Fabrication
-
Punchlist Activities
-
Commissioning Liquids Train
-
Previous activities
July - Aug
2021
-
Site paving – Concrete & asphalt
-
Installation of interior process mechanical equipment and piping
-
Raise site to sub grade and spread topsoil (weather permitting)
-
Process and electrical underground utilities
-
Pulling & terminating fiber backbone.
-
Installation of structural metals & grating
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures (BNR splitter remaining)
-
Interior finishes
-
Facility startup (Influent Pump Station, BBB/BNR, Solids & GT) Punchlist
-
Digester Lid #3 Fabrication
-
Punchlist Activities
Previous activities
June - July
2021
-
Site paving – Concrete & asphalt
-
Installation of interior process mechanical equipment and piping
-
Raise site to sub grade and spread topsoil (weather permitting)
-
Process and electrical underground utilities
-
Pulling & terminating fiber backbone.
-
Retaining wall near digesters
-
Structural concrete for wastewater treatment basins (Aeration steps remaining)
-
Installation of structural metals & grating
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures (BNR splitter remaining)
-
Interior finishes
-
Facility startup (Influent Pump Station, BBB/BNR, Solids & GT) Punchlist
-
Digester Lid #3 Fabrication
-
Punchlist Activities
Previous activities
May - June
2021
-
Site paving – Concrete & asphalt
-
Installation of interior process mechanical equipment and piping
-
Raise site to sub grade and spread topsoil (weather permitting)
-
Process and electrical underground utilities
-
Pulling & terminating fiber backbone.
-
Retaining wall near digesters
-
Structural concrete for wastewater treatment basins (Aeration steps remaining)
-
Installation of structural metals & grating
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures (BNR remaining)
-
Interior finishes
-
Facility startup (FDC, BBB/BNR, DCB, Solids & GT) Punchlist
-
Digester Lid #3
Previous activities
April - May
2021
-
Site paving – Concrete & asphalt
-
Installation of interior process mechanical equipment and piping
-
Raise site to sub grade and spread topsoil (weather permitting)
-
Process and electrical underground utilities
-
Pulling & terminating fiber backbone.
-
Retaining wall near digesters
-
Structural concrete for wastewater treatment basins (Aeration steps remaining)
-
Installation of structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures (BNR remaining)
-
Interior finishes
-
Facility startup (HW, FSPS, FDC, BBB/BNR, DCB & Solids) Punchlist
Previous activities
Mar - April
2021
​Site paving – Concrete & asphalt (pending plants opening)
Installation of interior process mechanical equipment and piping
Structural backfill of wastewater treatment buildings (Solids area)
Raise site to sub grade (weather permitting)
Process and electrical underground utilities
Pulling & terminating fiber backbone.
Retaining wall near digesters
Structural concrete for wastewater treatment basins (Aeration steps remaining)
Completion of building masonry
Installation of structural metals
Installation of interior ductwork, electrical conduit, and plumbing piping
Painting of interior walls and piping
Installation of electrical equipment
Water tightness testing of water-bearing structures (BNR, Digester 4 remaining)
Installation of roofing (IPS remaining)
Interior finishes
Facility startup (HW, FSPS & FDC)
Previous activities
Feb - Mar
2021
-
Site paving
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
Jan - Feb
2021
-
Site paving
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
Dec 2020 - Jan 2021
-
Site paving
-
Gutting of existing Influent Pump Station
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
Nov - Dec
2020
-
Site paving
-
Gutting of existing Influent Pump Station
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
Oct - Nov
2020
-
Site paving
-
Gutting of existing Influent Pump Station
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
Sept - Oct
2020
-
Reconstruction of Lee Boulevard – Roadway to be closed from Mission Rd to NB Lee Blvd and will be opening back up in September
-
Site paving
-
Demo of existing Maintenance Bldg and Switchgear, & gutting of existing Influent Pump Station
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
Aug - Sept
2020
-
Reconstruction of Lee Boulevard – Roadway to be closed from Mission Rd to NB Lee Blvd
-
Site paving
-
Demo of existing Maintenance Bldg and Switchgear, & gutting of existing Influent Pump Station
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
July - Aug
2020
-
Reconstruction of Lee Boulevard – Roadway to be closed from Mission Road to NB Lee Boulevard
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
June - July
2020
-
Reconstruction of Lee Boulevard – Roadway to be closed from Mission Road to NB Lee Boulevard
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Energization of the facility and initial equipment startup
Previous activities
May - June
2020
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Energization of the facility and initial equipment startup
Previous activities
April - May
2020
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Energization of new Evergy substation
Previous activities
Mar - April
2020
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Removal of the tower cranes
Previous activities
Feb - Mar
2020
-
Installation of interior process mechanical equipment and piping.
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls
Previous activities
Jan - Feb
2020
-
Installation of interior process mechanical equipment and piping.
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls
Previous activities
Nov - Dec
2019
-
Installation of interior process mechanical equipment and piping.
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
Previous activities
Sept - Oct
2019
-
Installation of interior process mechanical equipment and piping.
-
Excavations for new wastewater treatment basins, including rock excavation
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled piers
-
Installation of building masonry
Previous activities
Aug - Sept
2019
-
Installation of interior process mechanical equipment and piping.
-
Excavations for new wastewater treatment basins, including rock excavation
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled piers
-
Installation of building masonry
Previous activities
July - Aug
2019
​​
Installation of interior process mechanical equipment and piping
Excavations for new wastewater treatment basins, including rock excavation
Structural backfill of wastewater treatment buildings
Process and electrical underground utilities
Structural concrete for wastewater treatment basins
Drilled piers
Previous activities
Jun-July
2019
-
Excavations for new wastewater treatment basins, including rock excavation
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled piers
Previous activities
May - June
2019
-
Excavations for new wastewater treatment basins, including rock excavation
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled piers
Previous activities
Apr - May
2019
-
Excavations for new wastewater treatment basins, including rock excavation
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled Piers
-
Truck hauling of soils offsite
Previous activities
Mar - Apr
2019
-
Excavations for new wastewater treatment basins, including rock excavation
-
Demolition of existing wastewater treatment structures
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled piers
-
Truck hauling of soils offsite
-
Tower Crane Mobilization​
-
Tower Crane #3: March 2019
Previous activities
Feb - Mar
2019
-
Excavations for new wastewater treatment basins, including rock excavation
-
Demolition of existing wastewater treatment structures
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled Piers
-
Truck hauling of soils offsite
-
Tower Crane Mobilization:
-
Tower Crane #3: February 2019
Previous activities
Dec 2018 - Jan 2019
-
Excavations for new wastewater treatment basins, including rock excavation
-
Demolition of existing wastewater treatment structures
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled Piers
-
Tower Crane Mobilization:
-
Tower Crane #1: November 2018
-
Tower Crane #2: December 2018
-
Tower Crane #3: January 2019
Previous activities
Nov - Dec
2018
-
Excavations for new wastewater treatment basins, including rock excavation
-
Demolition of existing wastewater treatment structures
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled Piers
-
Tower crane mobilization:
-
Tower Crane #1: November 2018
-
Tower Crane #2: December 2018
-
Tower Crane #3: January 2019
Previous activities
Oct - Nov
2018
-
Installation of new traffic signal at Lee Blvd. & Mission
-
Excavations for new wastewater treatment basins, including rock excavation
-
Demolition of existing wastewater treatment structures
-
Process underground utilities
-
Structural concrete for wastewater treatment basins
-
Tower Crane Mobilization:
-
Tower Crane #1: November 2018
-
Tower Crane #2: December 2018
-
Tower Crane #3: January 2019
Previous activities
Sept - Oct
2018
-
Excavations for new wastewater treatment basins, including rock excavation
-
Demolition of existing wastewater treatment structures
-
Process underground utilities
-
Structural concrete for wastewater treatment basins
-
Completion of the Overflow Channel
-
Construction of the Trailer Complex
-
Installation of new traffic signal at Lee Blvd & Mission
Previous activities
Aug - Sept
2018
-
Excavations for new wastewater treatment basins
-
Demolition of existing wastewater treatment structures
-
Process underground utilities
-
Structural concrete for wastewater treatment basins
-
Completion of the Overflow Channel and install of temporary seeding
-
Secondary entrance installation along Lee Blvd
-
Use of soccer fields north of Lee Blvd for construction storage and laydown
Previous Activitiess
July - Aug
2018
-
Excavations for new wastewater treatment basins
-
Demolition of existing wastewater treatment structures
-
New process underground utilities
-
Structural Concrete for wastewater treatment basins
-
Finalizing decommissioning of Facility. Close attention will be paid to demolishing structures in order to minimize odors.
Previous Activities
June - July
2018
-
Utility relocations
-
Earthwork & Excavations
-
Decommissioning of existing plant
-
Demolition
-
Yard Piping
-
Structural Concrete
Previous Activities
May - June
2018
-
Site Fencing
-
Utility relocations
-
Earthwork
-
Demolition
-
Decommissioning of existing plant
-
24/7 Bypass pumping to occur the week of May 14th
Previous Activities
April - May
2018
-
Site Fencing
-
Utility relocations
-
Clear and Grub
-
Earthwork
-
Demolition
-
Decommissioning of existing plant
Groundbreaking Celebration
Thursday
April 12, 2018
For more information go to press release.